South Trees Inlet

QAL Waste Line 4 replacement Project

McConnell Dowell | 2021 November

Pipe placement and welding on the second last day of the QAL Waste Line 4 replacement project for McConnell Dowell. Barge “Steel Ranger” with FMG’s 60 Ton crane worked the shallows of the South Trees Inlet, to deliver pipes as required to the Client. Placement of the barge was with the multicat “Shackleton” and held in position with the spud arrangements.

Timing was the main factor due to the limited tidal range in the work area. Just over 600 metres of pipework was lifted into place, held when welded and lowered in a space of 4 weeks doing 5/6 day weeks.

FMG would like to congratulate McConnell Dowell on a well run project.

FMG Management thank all Contractors and Staff for another successful project completion.  